This conservation work forms part of the 10 Terminal and Parklands Renewal Project.
The work predominantly involves:
- Roof replacement, facade repairs and window refurbishment for buildings 1 and 3.
- General repairs and updates to conserve the heritage of buildings 1, 3 and 7.
 The target timeframe for the conservation work to be completed is September 2022.
The target timeframe for the conservation work to be completed is September 2022. 
The materials, colours and finishes used will respect the heritage of the buildings. This is a priority for the Harbour Trust.
Hours of work
The hours of all works, including delivery of materials to and from the site, is restricted as follows:
- Conservation work takes place between 7am and 6pm from Monday to Friday (inclusive).
- There is work between 7am and 1pm on Saturdays.
- There will be no work on Sundays and public holidays.
Reducing the impact of the conservation work
Noise: The Harbour Trust is working closely with the contractor to minimise disruptions to surrounding tenants and the public.
Traffic and access: The conservation work is not expected to impact on traffic, as the main site access occurs via the driveway between buildings 1 and 7 (see site map).
Carparks: Surrounding carparks should not be impacted by conservation works and all footpaths are anticipated to remain open.
If you have questions about the conservation work, please email info@harbourtrust.gov.au.
Click here for more information on the 10 Terminal and Parklands Renewal Project.